Location: Tioga County, PA
Project Description: Based on the Phase I ESA completed for the site, this assessment is limited to addressing potential impacts from one gasoline UST located on the site.
Project Solution: Based off the findings of the Phase I ESA, a Phase II ESA was recommended to determine if any environmental impacts have occurred to the site from the gasoline UST.
Specialized Equipment and Services: Soil borings and temporary monitoring wells were installed using direct push technology (i.e. Geoprobe). Encountered materials were screened for the potential presence of volatile organic compounds using a portable photoionization detector (PID).